Power Factor Correction
www.PowerFactorCorrection.net
To
advertise on this site, call/email
The Renewable Energy Institute

info@RenewableEnergyInstitute.org
What is
" Power Factor Correction?"
An
electric utility's power load on an electrical distribution system fall into one of three categories; resistive, inductive or capacitive. In
most industrial facilities, the most common power usages are "inductive."
Examples of inductive loads include transformers, fluorescent lighting and AC induction motors. Most inductive loads use a conductive coil winding to produce an electromagnetic
field which permits the motor to function.
What is "Power Factor?"
Power factor is a measure of how efficiently, or inefficiently, that
electrical power is used by a customer. For industrial customers, a low power factor
is generally caused by inductive loads such as transformers, electric motors and high-intensity discharge
lighting. Customers that do not use electrical power efficiently are being
charged additional fees for the inefficient use of power by their electric
utility company.
All inductive loads require two different types of power for the motor to operate:
Active power (measured in kW or kilowatts) - this power produces the motive force
Reactive power (kvar) - this energizes the magnetic field of the motor.
The operating power from the distribution system is composed of both active (working) and reactive (non-working) elements. The active power does useful work in driving the motor whereas the reactive power only provides the magnetic field.
Unfortunately, electric utility's customers are charged for both active
and reactive power.
Example: A customer's power factor drops, the system becomes less efficient. A drop from 1.0 to 0.9 results in 15%
more current being required for the same load. A power factor of 0.7 requires approximately
40% more current; and a power factor of 0.5 requires approximately 100% (twice as much) to handle the same load.
The answer to these problems is to reduce the reactive power drawn from the supply by improving the power factor.
If an AC motor were 100% efficient it would consume only active power.
However, since most AC motors are only 75% to 80% efficient, they operate at a lower power factor. This means
inefficient and even "wasteful" energy usage and cost efficiency because
most electric utilities charge penalties for poor, inefficient power factor.
Simply installing capacitors will improve a commercial or industrial
company's power factor and will result in savings on their electricity
bill every month!
Additional potential benefits for correcting poor power factor include:
Reduction of heating losses in transformers and distribution equipment
Longer equipment life
Stabilized voltage levels
Increased capacity of your existing system and equipment
Improved profitability
Lowered expenses
We
provide "EcoGeneration"
products, services and solutions that are Kyoto
Protocol compliant. This results in a Cooler,
Cleaner, Greener planet for everyone, as well as
decreased operating expenses and increased profits for the owners. Our
EcoGeneration
projects are also so environmentally safe, that we are classifying them as
"Pollution Free Powerprojects. Unlike most
companies, we are equipment supplier/vendor neutral. This means we help
our clients select the best equipment for their specific application. This
approach provides our customers with superior performance, decreased
operating expenses and increased return on investment.
Renewable
Energy Technologies provides
project development services that generate clean energy and significantly
reduce greenhouse gas emissions and
carbon dioxide emissions.
Included in this are our
turnkey "ecogeneration"
products and services which includes renewable
energy technologies, waste to energy,
waste to watts and waste
heat recovery solutions. Other project development
technologies include; Anaerobic Digester,
Anaerobic Lagoon, Biogas
Recovery, BioMethane, Biomass
Gasification, and Landfill Gas To
Energy, project development services.
Products and
services provided by Renewable Energy Technologies includes the following
power and energy project development services:
-
Project
Engineering Feasibility & Economic Analysis Studies
-
Engineering,
Procurement and Construction
-
Environmental
Engineering & Permitting
-
Project
Funding & Financing Options; including Equity Investment, Debt
Financing, Lease and Municipal Lease
-
Shared/Guaranteed
Savings Program with No Capital Investment from Qualified Clients
-
Project
Commissioning
-
3rd
Party Ownership and Project Development
-
Long-term
Service Agreements
-
Operations
& Maintenance
-
Green
Tag (Renewable Energy Credit, Carbon Dioxide Credits, Emission
Reduction Credits) Brokerage Services; Application and Permitting
For
more information: call us at: 832-758-0027
We
are Renewable Energy
Technologies specialists and develop clean power and energy projects
that will generate a "Renewable
Energy Credit," Carbon
Dioxide Credits and Emission
Reduction Credits. Some of our products and services solutions
and technologies include; Absorption
Chillers, Adsorption Chillers, Automated
Demand Response, Biodiesel
Refineries, Biofuel Refineries, Biomass
Gasification, BioMethane, Canola
Biodiesel, Coconut Biodiesel, Cogeneration,
Concentrating Solar Power, Demand
Response Programs, Demand Side
Management, Energy
Conservation Measures, Energy
Master Planning, Engine Driven
Chillers, Geothermal Heatpumps,
Groundsource Heatpumps, Solar
CHP, Solar Cogeneration, Rapeseed
Biodiesel, Solar Electric Heat
Pumps, Solar Electric Power
Systems, Solar Heating and
Cooling, Solar Trigeneration, Soy
Biodiesel, Trigeneration, and Watersource
Heatpumps.
Upgrading
Transmission Capacity
for Wholesale Electric Power Trade
On April 24, 1996, the Federal Energy Regulatory Commission (FERC) issued
a final rule, Order No. 888, in response to provisions of the Energy
Policy Act (EPACT) of 1992. Order No. 888 opens wholesale electric power
sales to competition. It requires utilities that own, control, or operate
transmission lines to file non-discriminatory open access tariffs that
offer others the same electricity transmission service they provide
themselves. The second final rule, Order No. 889, issued on the same date,
requires a real-time information system to assure that transmission owners
and their affiliates do not have an unfair competitive advantage in using
transmission to sell power. It is expected that Orders No. 888 and No. 889
and other actions taken by State Public Service Commissions to promote
competition in the electric power industry will result in increased
demands for transmission services.
EPACT
states that when transmission capacity is constrained, an electric utility
must offer to enlarge its transmission capacity, if necessary, to provide
transmission services. However, obtaining approval to site and build new
transmission capacity is becoming more difficult due to environmental
concerns, potential health effects of electric and magnetic fields (EMF),
special interest groups' concerns, and the concern that property values
would decline along transmission line routes. Currently, 10,126.8 line
miles of transmission additions are planned for the United States, Canada,
and the northern portion of Baja California, Mexico, for 1995 through 2004
and are in different stages of planning and/or construction. Many of these
lines may be delayed for many years or may never be constructed.
Due
to the problems associated with constructing new transmission lines, it is
important to examine .the possible options for increasing the transmission
capability on present sites and making maximum use of existing
transmission systems through upgrades. When feasible, upgrades are an
attractive alternative, because the costs and leadtimes are less than
those for constructing new transmission lines. This article describes to
policy makers and regulators the bulk electric power system and identifies
the thermal, voltage, and operating constraints on a system's capability
to transmit power from one area to another. Some of the potential remedies
for these constraints through upgrades are presented along with a
comparison of the cost to upgrade compared to the costs for new
transmission lines.
Description
of the Bulk Electric Power System
The
basic elements of an electric power system are shown in (Note that the
figure does not include all types of electric generation.) The electric
generating plants or stations, transmission lines, and high voltage or
bulk power substations that constitute the bulk power system are shown
above the dashed line. Subtransmission and distribution systems and sites
where the electricity is consumed is shown below the dashed line.
Transmission lines and distribution lines are categorized by their voltage
rating. Transmission lines are generally defined as 115 kilovolts (kV) and
higher (765 kV is the highest installed). Subtransmission systems are 69
kV to 138 kV. Distribution systems, that furnish power to retail
customers, are less than 69 kV.
The
transmission system usually designates the highest voltage or voltages
used on a given system and carries electric energy from the power plants
to the distribution system. Most transmission systems use overhead
alternating current (AC) lines; however, some overhead direct current
transmission systems and underground and submarine cable exist as well.
Power transformers are used in generating stations to raise the voltage of
the produced power from the generation voltage to transmission voltage; in
distribution substations to reduce the voltage of the power delivered to
the distribution system voltage; and elsewhere to connect together
transmission systems designed at different voltages.
The
bulk-power substation supplies power to the subtransmission system, the
part of the system between transmission and distribution systems. The
distribution system carries the electricity to the residential and
commercial customers and some of the smaller industrial customers.
Switching
stations and substations are used to transform the electrical energy to a
different voltage, transfer electrical energy from one line to another,
and to redirect the flow of power whenever a fault occurs on the
transmission line or other equipment in the system, so system operation
can be preserved. Circuit breakers disconnect the flow of power from the
faulted equipment protecting it from further damage.
A
control center coordinates the operation of bulk power system components
and is responsible for .operating the power system within a geographic
region called a control area. One or more utilities make up a control
area. A control center is connected to other control centers with
transmission tie lines. Through proper communications (metering and
telemetry), the control center is constantly informed of generating plant
output, transmission lines and ties to neighboring systems, and system
conditions. A control center uses this information to ensure reliability
by following reliability criteria and to maintain its interchange schedule
with other control centers.
For
the bulk power system to operate reliably, it must be designed and
operated based on the following principles:
-
The
total generation at any moment must be kept equal to total electricity
consumption and losses on the system including transmission and
distribution.
-
The
electricity is allowed to flow through the transmission system in
accordance with physical laws and cannot be directed to flow through
specific lines.
-
The
system must be designed with reserve capacity in generation and
transmission to allow for .uninterrupted service when contingencies
occur.
Constraints
on the Transmission System
The
amount of power on a transmission line is the product of the voltage and
the current and a hard-to-control factor called the "power
factor." Additional power can be transmitted reliably if there is
sufficient available transfer capability on all lines in the system over
which the power would flow to accommodate the increase and certain
contingencies or failures that could occur on the system. There are three
types of constraints that limit the power transfer capability of the
transmission system: thermal/current constraints, voltage constraints, and
system operating constraints.
Thermal/Current
Constraints
Thermal
limitations are the most common constraints that limit the capability of a
transmission line, cable, or transformer to carry power. The transmission
line resists the flow of electrons through it, causing heat to be
produced. The actual temperatures occurring in the transmission line
equipment depend on the current, that is the rate of flow of the
electrons, and also on ambient weather conditions, such as temperature,
wind speed, and wind direction, because the weather effects the
dissipation of the heat into the air. The thermal ratings for transmission
lines, however, are usually expressed in terms of current flows, rather
than actual temperatures for ease of measurement.
Thermal
limits are imposed because overheating leads to two possible problems: (1)
the transmission line loses strength because of overheating which can
reduce the expected life of the line, and (2) the transmission line
expands and sags in the center of each span between the supporting towers.
If the temperature is repeatedly too high, an overhead line will
permanently stretch and may cause its clearance from the ground to be less
than required for safety reasons. Because this overheating is a gradual
process, higher current flows can be allowed for limited time periods. A
"normal" thermal rating for a line is the current flow level it
can support indefinitely. Emergency ratings are levels the line can
support for specific periods, for example, several hours.
Underground
cables and power transformers are also limited by thermal constraints.
Operating undergroundcables at excess temperatures shortens their service
lives considerably due to damage to their insulation. Power transformers
are likewise designed to operate at a maximum temperature rise to protect
insulation.
Voltage
Constraints
Voltage,
a pressure-like quantity, is a measure of the electromotive force
necessary to maintain a flow of electricity on a transmission line.
Voltage fluctuations can occur due to variations in electricity demand and
to failures on transmission or distribution lines. Constraints on the
maximum voltage levels are set by the design of the transmission line. If
the maximum is exceeded, short circuits, radio interference, and noise may
occur. Also, transformers and other equipment at the substations and/or
customer facilities may be damaged or destroyed. Minimum voltage
constraints also exist based on the power requirements of the customers.
Low voltages cause inadequate operation of customer's equipment and may
damage motors.
Voltage
on a transmission line tends to "drop" from the sending end to
the receiving end. The voltage drop along the AC line is almost directly
proportional to reactive power flows and line reactance. The line
reactance increases with the length of the line. Capacitors and inductive
reactors are installed, as needed, on lines to, in part, control the
amount of voltage drop. This is important because voltage levels and
current levels determine the power that can be delivered to the customers.
System
Operating Constraints
The
operating constraints of bulk power systems stem primarily from concerns
with security and reliability. These concerns are related to maintaining
the power flows in the transmission and distribution lines of a network.
Power flow patterns redistribute when demands change, when generation
patterns change, or when the transmission or distribution system is
altered due to a circuit being switched or put out of service.
Power
Flows in Networks
When
one utility, or control area, transmits power to another, the resulting
power flows along all paths joining the two areas, regardless of ownership
of the lines. The amount of power flowing on each path of the transmission
system depends on the impedance of the various paths. The impedance of a
transmission line depends on the line's length and design details for the
line. A low impedance path attracts a greater part of the total transfer
than a path with a high impedance.
When
utilities enter into a wholesale power transaction with other utilities,
nonutilities, or customers they designate a pro forma "contract
path" of transmission lines or systems through which the power is
expected to flow. The actual power flows from the transactions, however,
do not necessarily follow the contract path but may flow through parallel
paths in other transmission systems depending on the loading conditions at
the time when the transfer occurs. These are referred to as "parallel
path flows." When transmission systems are directly or indirectly
interconnected with each other at more than one point, power flows can
travel into the other systems' networks and return, thus forming
"loop flows." Both loop flows and parallel path flows may limit
the amount of power these other systems can transfer for their own
purpose.
Preventive
Operation for System Security
Constraints
on the transmission capabilities also occur due to preventive operating
procedures for system security. The bulk power system is designed and
operated to provide continuity of service in the case of possible
contingencies such as: loss of a generation unit, loss of a transmission
line, or a failure of any other single component of the system.
"Preventive" operating procedures means operating the system in
such a way as to avoid service interruptions as a result of certain
component outages. It is recognized as good utility practice and regarded
by the North American Electric Reliability Council (NERC) as the primary
means of preventing disturbances in one area from causing service failures
in another. NERC provides standards and operating
guidelines for overall coordination of utility procedures in the United
States, Canada, and parts of Mexico.
The
NERC guidelines recommend making it an operational requirement that
systems be able to handle any single contingency. The ability to handle
multiplecontingencies should be an operational requirement when practical,
according to NERC. The adoption of the NERC guidelines has increased the
operating security of the interconnected systems and reduced the frequency
with which major disturbances occur.
The
NERC preventive operating requirements include running sufficient
generation capability to provide operating reserves in excess of demand
and limiting power transfers on the transmission system. The system then
operates so that each element remains below normal thermal limits under
normal conditions and under emergency limits during contingencies. The
reserve capacity can then be used to handle contingencies.
System
Stability
Power
systems stability problems represent other system operating constraints.
Generally they are grouped into two types:
In
a synchronous, interconnected operating system, all generators rotate in
unison at a speed that produces a consistent frequency. In the United
States, this frequency is 60 cycles per second. When a disturbance (fault)
occurs in the transmission system, the power requirements from the
generators change. The fault may reduce the power requirements from the
generator; however, the mechanical power driving the turbine stays
constant, causing the generator to accelerate. Removing the fault alters
the power flow and the turbine slows down. This results in oscillations in
the speed at which the generator rotates and in the frequency of the power
flows in the system. Unless natural conditions or control systems damp out
the oscillations, the system is unstable. This is referred to as transient
instability and may lead to a complete collapse of the system. To avoid
transient instability, power transfers between areas are limited to levels
determined by system contingency studies. Steady-state instability can
occur if too much power is transferred over a transmission line or part of
a system to the point that the synchronizing forces are no longer
effective. Steady-state instability is an unusual occurrence because it is
easily preventable; however, it acts as a constraint on transmission power
transfers. Small-signal instability, also called dynamic instability,
usually occurs when normal variations in generation or consumption are too
small to be considered disturbances, but initiate oscillations at low
frequencies. These conditions can lead to large voltage and frequency
fluctuations, resulting in loss of overall system stability.
Voltage
instability occurs when the transmission system is not adequately designed
to handle reactive power flows. Large amounts of reactive power flows on
long transmission lines result in severe drops in voltage at the
consumption end, causing the consuming entities to draw increasing
currents. The increased currents cause additional reactive power flows and
voltage losses in the system, leading to still lower voltages at the
consumption end. As the process continues, the voltages collapse further,
requiring users to be disconnected to prevent serious damage. Finally, the
system partially or fully collapses.
Upgrade
Remedies for Constraints on the Transmission System
The
constraints, that have been described, limit a system's ability to
transfer power and, therefore, lower the utilization rates of the existing
transmission network. This section of the report will discuss upgrade
possibilities to increase the transfer capability of existing transmission
lines so that additional power can be transmitted reliably from one area
of a system to another, or from one entire system to another. Remedies for
constraints related to thermal limits, voltage-related limits, other
options to increase power transfer, and system operating procedures will
be explained and the typical costs of these remedies provided. The typical
cost of building a new transmission line is also included for comparison.
Note that actual costs for a specific project could be somewhat higher or
lower than those shown in the table. Right-of-way costs, that is the cost
of land and the legal right to use and service the land on which the
transmission line would be located, are not included in the table because
they vary significantly depending on the location and the territory being
traversed. New line costs are substantial, however, even without the
inclusion of the costs of rights-of-way.
Remedies
for Thermal Constraints on Components
Many
options are available for reducing the limitations on power transfers due
to the thermal rating of overhead transmission lines. Available measures
are much more limited for underground cables and transformers. A review of
the process used to set the present thermal rating for a transmission line
may reveal ways to increase the rating at little or no cost. In the past,
it was common practice to use approximations and simplifications to
determine thermal ratings for lines, with the result that the lowest
possible rating and greatest reliability were selected. Modern methods for
computing thermal ratings for different conditions may allow higher
ratings without any physical changes to the line.
In
addition, power flow limits for lines based on reaching a maximum
temperature can be calculated in real-time using data on the ambient
weather conditions on the line and power flow information available to the
control center. Some utilities measure the temperature of the line using
detectors located on the transmission lines and transmit it to the control
center. One estimate for such a system, including sensors and ground
installation, was $70,000 per location.
Since
the thermal limit of a transmission line is based on the component that
would be the first to overheat, a substantial increase in the overall
thermal rating of the line can sometimes result from replacing an
inexpensive element. The replacement of a disconnect switch or circuit
breaker is much less costly than major work to replace a line or to build
a new line. The parts being replaced can often be used somewhere else on
the system.
It
may be acceptable to increase allowable temperatures and plan for a
decrease in the life of the lines. This approach may produce sags in the
line such that the allowable clearance to the ground is not maintained. If
inadequate clearances occur at a limited number of spans on the line, it
may be economically justifiable to rebuild the towers, increasing their
height to restore sag clearances, or to fence the affected parts of the
right-of-way to make them inaccessible. If the excessive sag occurs
throughout the line, however, increasing the height of towers would be
very expensive. Sometimes it is possible to re-tension the line or span to
increase the clearance to the ground.
It
may also be possible to increase the transfer capability of the line by
monitoring the line sag to allow higher temperatures/currents. There are
two possible approaches one direct and another indirect. The direct
approach involves calculating the actual sag of the line at its mid-span
using actual information provided by special sensors on the towers about
the horizontal tension and ambient temperature. Using this method, the
control center calculates the actual limit on the current that the line
can handle under actual conditions. The indirect method entails
transmitting temperatures and wind velocity and locations of the critical
sag sites to the control center by radio or telephone. With this
information, the control center calculates what the sag is and determines
any dangerous trend.
The
most obvious, but also most expensive method for alleviating the thermal
constraints on a line is to replace the lines with larger ones
(conductors) through "restringing" or to add one or more lines,
forming "bundled" lines. This approach requires consideration of
the tower structures that support power lines. The towers are designed to
hold the weight of the existing lines and the weight of any possible ice
formations. They require lateral strength to withstand the sometimes very
substantial forces of winds blowing perpendicular to the direction of the
line. Replacing lines with larger ones, or bundling them, usually requires
substantial reinforcement of the tower structures and, possibly, the
concrete footings of the towers. Restringing or bundling lines to increase
the transfer capability also requires enhancing substation equipment so
that it does not become a limiting factor. Substation enhancements cost
approximately $600,000 per substation.
Other
typical cost estimates for restringing transmission lines with larger
conductors are:
-
60
kV line, to 397.5 kcmil: $40,000 per mile
-
115
kV line, to 715.5 kcmil: $80,000 per mile
-
230
kV line, to 1,113 kcmil: $120,000 per mile.
The
normal thermal ratings of the restringed lines would be approximately 55
MW, 150 MW, and 400 MW, respectively.
Some
typical costs of bundling lines are:
-
115
kV line, 715.5 kcmil: $130,000 per mile
-
230
kV line, 1,113 kcmil: $200,000 per mile
-
230
kV line, 2,300 kcmil: $260,000 per mile.
Bundling
these lines would approximately double their normal thermal ratings, for
an increase of approximately 150 MW, 400 MW, and 500 MW,
respectively.
Remedies
for Voltage Constraints for Individual Lines
The
standard voltages for electric utility lines in the United States are
currently 34.5 kV, 46 kV, 69 kV, 115 kV, 138 kV, 161 kV, 230 kV, 345 kV,
500 kV, 765 kV, and 1,100 kV (not yet commercially installed). Each of
these line types can carry 5 percent more or less voltage for normal
operation. Upgrades to change line voltages can be divided into two
categories: increases within a voltage class and changes to a different
voltage class.
Increasing
the operating voltage within a voltage class is a technique that has been
used for decades. If the system does not reach the upper voltage limit
during light loads under normal operation, normal operating voltage can be
increased without major configuration changes to the lines. It is
necessary, however, to increase the voltages of the generators, and to
make some adjustments to the settings of the transformer, or possibly some
transformer replacements, in order to produce the new operating voltage.
Coordination with neighboring systems is required to prevent additional
reactive power flows because of the increased voltage into the neighboring
system.
Other
remedies for voltage problems that limit transfer capabilities involve
controlling reactive power flows. There are two types of reactive power
sources, capacitors, and reactors, which generate and absorb reactive
power flows, respectively. The installation of capacitors or reactors at
strategic locations of the transmission or distribution system, is a
remedy often used to control reactive power flows and therefore increase
power transfers. Shunt capacitor installation costs are shown below:
-
115
kV, 50 megavolt amperes reactive (MVAR): New installation, $1,000,000;
additional step (more capacitors) in existing installation, $500,000
-
230
kV, 63 MVAR: New installation, $2,000,000; additional step, $700,000
-
500
kV, 100 MVAR: New installation, $3,000,000
-
500
kV, 200 MVAR: New installation, $5,000,000.
Typical
costs of shunt reactors on the transmission line are:
-
230
kV, 87.9 MVAR: New installation, $2,000,000
-
500
kV, 100 MVAR: New installation, $3,000,000.
Voltage
changes to a higher voltage class usually require substantial
reconstruction of the transmission lines. Higher voltages require greater
clearances between the lines, and between grounded objects including the
towers. Increasing the string of insulators and making other changes drive
up the weight and transverse loadings of the towers. These changes require
additional strength in the construction of the towers and their footings.
Typical estimates for converting steel tower transmission lines from one
voltage class to another are:
-
60
kV to 115 kV: $50,000 per mile
-
115
kV to 230 kV: $500,000 per mile
-
230
kV to 500 kV: $800,000 per mile.
Voltage
class conversions increase normal thermal ratings which depend on the
conductor size. The following are typical values of increases that can be
achieved:
-
60
kV to 115 kV, 397.5 kcmil conductors: from 56 MW to 108 MW; 115 kV to
230 kV, 715.5 kcmil .conductors: from 151 MW to 302 MW; and
-
230
kV to 500 kV, 1,113 kcmil conductors: from 400 MW to 865 MW.
Rebuilding
a line to higher voltage requires further expense for substation
equipment. If the connected networks remain at the older voltage,
rebuilding a line to higher voltage would require a transformer at either
end to provide connection to the rest of the system. Rebuilding a line for
higher voltage class is not cost-effective unless a number of circuits are
converted at the same time.
Other
Options to Increase Power Transfer
Other
methods of mitigating power transfer constraints due to individual
components include: converting single circuit towers to multiple-circuit
towers and converting alternating current (AC) lines to high-voltage
direct current (HVDC) lines. Most transmission circuits for 230 kV and
below are built on two-circuit tower lines. Circuits for higher voltages
are generally built on single-circuit towers. Substantial increases in
either right-of-way width or in tower height are required for conversion
of a single-circuit line to a double-circuit line. Estimates of the costs
of conversion are given on
The
conversion of an AC line to HVDC, or the replacement of an AC line, is a
consideration when large amounts of power are transmitted over long
distances. HVDC lines are connected to AC systems through converter
systems at each end. The power is converted from AC to DC at the sending
end and back to AC at the receiving end. HVDC circuits have some
advantages over AC circuits for transferring large amounts of power. HVDC
circuits can be controlled to carry a specific amount of power without
regard to the operation of the AC circuits to which they are connected. If
HVDC lines are operating in parallel with AC lines, the outage of a
parallel AC line does not overload the DC line. However, the outage of the
HVDC line does increase the loading on the parallel AC lines. HVDC
circuits have resistance but do not have reactance associated with AC, so
they have less voltage drop than AC circuits. HVDC circuits have a major
disadvantage as they require converter stations at each end of the circuit
that are very expensive, making HVDC uneconomical except when power is
transmitted for long distances. HVDC circuits also do not have the system
instability problems that AC circuits have.
Remedies
for System Operating Constraints
Changing
Power Flows
As
previously mentioned, the distribution of power flows through a
transmission network depends on the impedance of the different lines. If
the power flows over the system can be changed so that the loading on a
critical line is reduced, larger power transfers can be permitted.
Sometimes the power flows through a transmission system can be improved by
changing the connections of lines at various substations to increase power
flow through some lines and reduce it in others. Some reconfigurations,
such as closing some circuit breakers and opening others, require no
investment. Other reconfigurations require small investments such as the
addition of some circuit breakers or the reconnection of a line from one
bus in a substation to another.
There
frequently are multiple paths between sections of the transmission system.
A single line often becomes overloaded before the others. Some devices can
also be used to address this problem and change the power flows; the
phase-angle regulator (PAR) is the device most often used. PAR is also
referred to as a power-angle regulator, or phase shifter. A PAR looks like
atransformer and induces a circulating power flow through the regulated
line and back through all lines that are more or less in parallel with it.
The distribution of the current flows over the lines is changed, but the
total power transfer is not. The use of PARs has increased in recent
years; however, their installations are relatively costly. A 230-kV,
300-MVA PAR with a phase angle capability of plus or minus 60 degrees is
estimated at $30,000,000.
The
power flow can also be altered by reducing the impedance of the line by
inserting a series capacitor or increasing the impedance by inserting a
series reactor (actually a coil). Series capacitors are often used on long
transmission lines to reduce impedance, thus reducing the voltage drop
along the line and decreasing the amount of losses due to reactive power.
Capacitors increase the flow of power on the line on which they are
inserted and reduce the power flow on other parallel lines. A 500 kV, 570
million volt amperes reactive (MVAR) capacitor installation was recently
estimated at $10,000,000. Series reactors reduce the power flowing through
a line which otherwise would be overloaded, but are used less often than
capacitors. Series reactors are often used to limit short circuit
currents. They have one disadvantage in that they increase the voltage
drop on the line reducing power transfer capability.
Change
in Operating Philosophies
The
"preventive" operating procedure, discussed under system
operating constraints, ensures that no action is required in the event of
a system contingency other than clearing the fault. When contingencies
arise, the system is capable of responding without lines overheating,
voltage problems, and instability. This approach is different from
"corrective" operation, which requires immediate action, such as
switching circuits or other actions, after a contingency occurs, so the
system performance will be adequate. Corrective operation is less reliable
than preventive operation, but allows greater power transfers during
normal operations. Corrective measures between systems sometimes become so
complex that when a certain contingency occurs, the system fails.
Changing
the power flows over the system to reduce the loading on the critical line
after a contingency occurs increases the power transfers that can be made
under normal conditions. The improvement in the power flows must be
compared against the cost of system failures when the corrective measures
do not work. Technologies are being developed to move toward corrective,
rather than preventive methods. Technologies, developed as a part of a
Flexible AC Transmission System, (FACTS), can be used to help mitigate
current preventive system operating constraints. The FACTS concept uses
new power-electronics switches and other devices to provide faster and
finer controls of equipment to change the way the system power flows
divide over the system under normal conditions or during contingencies. A
FACTS device can be used to reduce the flow on the overloaded line and
increase the utilization of the alternative paths excess capacity. This
allows for increased transfer capability in existing transmission and
distribution systems under normal conditions. Some FACTS applications are
presently feasible and in service while others are in various stages of
development.
Increasing
Stability Limits
Various
schemes are available to increase the ability to withstand power system
transient instability. These measures reduce the power mismatch between
generation and consumption levels in different regions of the power
system. The following describes some technologies for generators and their
controls that influence the transient stability performance of the power
system.
The
new relatively small simple cycle and combined-cycle turbines, which are
dispersed throughout the power system, can improve the stability of the
system because of their fast response. These generators have little
inertia and fast-acting mechanical drives, allowing them to change their
generation level rapidly compared with older fossil-fuel steam plants.
Dispersed generation usually reduces both power transfers between regions
of the power system and power imbalance in each region. Dispersed
generation also allows for a more uniform distribution of overall system
inertia. Finally, the faster response of the generators can better follow
demand variations in their region.
Transient
stability can also be maintained by two generator control systems. The
automatic voltage regulator (AVR) control system is responsible for
maintaining a fixed voltage from the generator regardless of demand
levels. AVR's contribute to keeping the power system within stability
limits in the face of faults. The governor control system regulates the
mechanical power outputof the generator's mechanical drive or turbine. If
the generator rotor speed drops in a steam power plant, the governor
increases the steam flow to the turbine, which increases the mechanical
power delivered to the generator. Conversely, an increase in rotor speed
is countered with a reduction in steam flow and turbine mechanical power.
The control systems help to maintain the synchronous speed of generators
in a region and improve the stability performance of the overall system.
Transient
stability in systems with more than one long transmission line can be
increased by inserting one or more switching stations. For example, if one
of a pair of long lines is lost due to a fault, the path of these two
lines now has an impedance twice (200 percent) what it was before one line
failed. This can have a serious effect on the stability of the system. If
a switching station is installed on both lines and a fault occurs on one
line, the two lines will now have 150 percent of the original impedance
when the fault is cleared. This is a substantial contribution to the
stability of the system and allows a substantial increase in the transfer
of power.
Transient
instability is a major concern of system operators because it is the most
common source of instability and because changes in operating conditions
produce the greatest variation in stability constraints. If system
limitations can be calculated for actual conditions rather than off line,
the system can be operated closer to actually needed limitations. These
calculations require on-line data that provide immediate measurements of
actual loading, generation, and transmission system status. Some utilities
perform their off-line dynamic security studies every day based on the
operating conditions forecast for the next day. The results of these
studies, which are usually performed overnight, are provided to the
control center for operating the power system the next day. On-line
dynamic security assessment eliminates all conservative assumptions about
future operating conditions because actual data on system operating
conditions are used. This on-line assessment can increase the actual
transfer capability of a power system.
Conclusion
Utilities
are expecting increased competition in the future and are looking for ways
to lower their costs. The option to increase transmission capacity by
upgrading the existing lines is of interest because it can be done at
considerably less cost than constructing a new transmission line and with
a shorter lead time. Also, constructing new transmission lines is becoming
more difficult with environmental concerns, potential health effects of
EMF, and possibly declining property values over transmission line routes.
The transfer capability of a system may be increased if the thermal,
voltage, or system operating constraints of the existing transmission
lines can be removed with some of the upgrade remedies described herein.
As restructuring of the electric power industry for increased competition
continues, along with increases of wholesale trade, it is expected that
the future operators of the transmission system, whether they are
independent system operators (ISOs), regional transmission groups (RTGs),
power pools, or utilities, will be interested in increasing the
utilization rates of the existing transmission lines using some of the
options described in this article.
* From the Department of Energy
and Energy Information Administration websites with permission
|